Projects under annual programmes 2007-2011

Estonian Ministry of the Interior has approved the following projects to be co-financed under annual programmes 2007-2011 of External Borders Fund:
AP 2011 | Final beneficiary | Name of the project | Estimated amount of Community funding (EUR) | Estimated amount of public funding (EUR) |
1. | The Police and Border Guard Board | II stage of the video surveillance system for the Gulf of Kulje | 313 966 | 104 655 |
2. | The Police and Border Guard Board | Training of border guard officials | 71 900 | 23 967 |
3. | The Police and Border Guard Board | The construction of a cordon and a helicopter hangar on a blue external border | 1 301 293 | 1 172 862 |
4. | The Police and Border Guard Board | Renovation of the Lake Peipsi integrated surveillance system | 254 063 | 84 688 |
5. | The Police and Border Guard Board | Implementing the II stage of the Maritime Surveillance Information System | 397 947 | 132 649 |
6. | The Police and Border Guard Board | Procurement of a fully automated border control equipment | 335 536 | 111 845 |
7 | IT and Development Centre of the Ministry of the Interior | Activation of SIS II | 479 337 | 562 422 |
8 | IT and Development Centre of the Ministry of the Interior | Exchanging the software and database platform of the Border Control Information System | 143 801 | 47 934 |
AP 2010 | Final beneficiary | Name of the project | Estimated amount of Community funding (EUR) | Estimated amount of public funding (EUR) |
1. | The Police and Border Guard Board* | Procurement of a helicopter | 2 999 873 | 4 794 925 |
2. | The Police and Border Guard Board | Elaboration of Border Guard Information System | 143 801 | 47 935 |
3. | The Police and Border Guard Board | The construction of a cordon and a helicopter hangar on a blue external border | 47 934 | 15 978 |
*until 31.12.2009 there were three separate institutions (The Board of Border Guards, The Police Board and The Citizenship and Migration Board) which were merged into one – the Police and Border Guard Board – from 01.01.2010.
AP 2009 | Final beneficiary | Name of the project | Estimated amount of Community funding (EUR) | Estimated amount of public funding (EUR) |
1. | Board of Border Guard | Procurement of a helicopter | 3 234 398 | 1 078 133 |
2. | Board of Border Guard | Elaboration of Border Guard Information System | 143 801 | 47 935 |
AP 2008 | Final beneficiary | Name of the project | Estimated amount of Community funding (EUR) | Estimated amount of public funding (EUR) |
1. | Board of Border Guard | Procurement of a helicopter | 2 367 714 | 997 913 |
2. | Board of Border Guard | Elaboration of Border Guard Information System | 143 801 | 47 934 |
AP 2007 | Final beneficiary | Name of the project | Estimated amount of Community funding (EUR) | Estimated amount of public funding (EUR) |
1. | Board of Border Guard | Updating vessels communication and navigation systems | 190 416 | 63 472 |
2. | Board of Border Guard | Renovating border guard vessel PVL-107 “KÕU” | 100 661 | 33 554 |
3. | Board of Border Guard | Renovating border guard vessel PVL-109 “VALVAS” | 234 875 | 78 292 |
4. | Board of Border Guard | Renovating the surveillance system at Narva city dry river bed | 431 404 | 143 801 |
5. | Board of Border Guard | Creating an integrated surveillance system for Lake Lämmijärv with the control centre at Mehikoorma Border Station | 527 271 | 175 757 |
6. | Board of Border Guard | Purchasing and installing two 3-phase UPS-s | 19 173 | 6 391 |
7. | Board of Border Guard | Video surveillance system for Gulf of Kulje | 143 801 | 47 938 |
8. | Board of Border Guard | Renovating Mehikoorma border station | 208 368 | 69 456 |
9. | Board of Border Guard | Developments of Border Guard Information System for linking it with SIS II | 124 628 | 41 543 |
10. | Police Board | Development of information systems for SIS II | 335 536 | 179 946 |